You’ve decided the office needs door access — keycards, fobs, or phones instead of metal keys. Here’s exactly what the project looks like from first call to handing credentials to your team, so nothing on install day is a surprise.
Step 1 — The walk-through (30–60 minutes)
Someone needs to physically look at your doors before quoting. Door material (wood, hollow metal, aluminum storefront, frameless glass), frame condition, ceiling access for wiring, where the controller can live, and the path back to your network closet. A quote produced without a walk-through — or at least detailed photos and a video call — is a guess, and guesses become change orders.
Expect questions about how many people need access, how often staff turn over, and whether you want one system to also run cameras later. Answer honestly; the design follows.
Step 2 — Design and the fixed quote (2–5 days)
A proper proposal names the reader model, the locking hardware per door (electric strike vs maglock — the door type decides), the controller, credential type, and three things weak quotes omit:
- Egress hardware: any door people exit through needs code-compliant release — push-to-exit, request-to-exit sensor, and fail-safe locking that opens when power drops.
- Fire-alarm coordination: maglocked egress doors typically must release on fire alarm. If your building’s panel is serviced by an incumbent fire vendor, that tie-in is scheduled with them — it should be named in the quote as included or excluded, never silent.
- The permit: low-voltage work is permitted in most jurisdictions. The quote should say who pulls it and who stands the inspection.
Step 3 — Scheduling (1–3 weeks out, typically)
Hardware gets ordered, the permit filed, and if a fire-alarm vendor is involved their service call gets coordinated to land the same week. For occupied offices, work is scheduled around your hours — door hardware swaps are noisy for an hour per door.
Step 4 — Install day (half day for 1–2 doors; a day or two for a suite)
What actually happens: low-voltage cable is pulled from each door to the controller; locking hardware mounts on the door and frame; the reader mounts beside the door; exit hardware goes on the secure side; the controller lands in your network closet on its own power. Your door stays functional throughout — crews rig temporary access so the office keeps moving. End of day, every cable is labeled and the mess is gone. That last sentence should be true; make sure your installer agrees in writing.
Step 5 — Programming and testing (same day or next)
Credentials load into the system — every employee gets a card, fob, or mobile pass; access schedules get set (cleaning crew weekday evenings only, server room limited to two people, front door auto-unlocks for business hours if you want it). Then the tests: every credential on every door, exit hardware, door-held-open alerts, and — for maglocked egress doors — the witnessed release test: power cut, alarm trip, door opens. If an inspector needs to witness it, that’s scheduled here.
Step 6 — Handoff (don’t skip this)
Someone on your team learns to add and revoke users, pull an access log, and change a schedule — it’s a ten-minute skill in modern systems. You get the admin login, the wiring documentation, and the answer to the only question that matters later: “who do we call when a reader acts up?”
What can go sideways (and how to keep it from happening)
- The glass door discovery. Tempered glass can’t be drilled — frameless doors need surface-mount maglocks and brackets. Caught at the walk-through, it’s a line item. Caught on install day, it’s a delay.
- The dealer-locked fire panel. Only the incumbent vendor can touch some panels. Good installers identify the fire vendor during design, not after.
- The offline question. Ask what happens when the internet drops. The right answer: doors keep working — controllers hold the credential database locally and sync when the connection returns.
Timeline at a glance
| Phase | Typical duration |
|---|---|
| Walk-through → quote | 2–5 days |
| Quote → install day | 1–3 weeks (hardware + permit + coordination) |
| Install | 0.5–2 days for most offices |
| Programming, testing, handoff | same day – next day |
Related from ClearMax
- What access control actually costs in 2026
- Our access control installation service
- Keycard vs fob vs mobile credentials
Ready for the walk-through? Call (833) 306-3168 — we answer, and we can usually look at your doors within a couple of days.