Office Move IT Checklist: What to Do and When

The short answer: order the internet circuit for the new address the week you sign the lease, get cabling run while the walls and ceilings are still open, start phone number porting at least a month out, install and test the network before move weekend, and cut over outside business hours. Everything else on an office move IT checklist fits around those five steps.

As soon as the lease is signed (60–90+ days out)

While construction is underway (30–60 days out)

Two to three weeks out

Move weekend

First week at the new office

The three items that cause most move-day failures

  1. The circuit was ordered late. It is the longest lead item and can’t be rushed.
  2. Porting wasn’t started. The phones ring at an empty office.
  3. Cabling didn’t match the final layout. Desks end up far from the drops.

Moving an office in Central Ohio? We plan and run the IT side of the move from the circuit order through cutover. See office IT relocation services, or read about a network infrastructure upgrade if you’re replacing equipment at the same time.

Planning this for your office?

Start with a free assessment. You get a written plan and an itemized quote.

Book a free assessment →

6306 Marsh Wren Dr, Gahanna, OH 43230 · (833) 306-3168 · ClearMax Labs