Almost every expensive IT problem in a new office traces back to a decision nobody made early enough. This is the sequence we walk clients through, ordered by when it has to happen.
Before the lease is signed
- Check what internet is actually available at the address. Not what is available on the street — at the suite. Fiber a block away is not fiber in your building, and a business that needs symmetrical bandwidth can sign a lease that makes it impossible. This is the single most expensive thing to discover late.
- Find out who owns the demarc and the IT closet. In multi-tenant buildings, where the carrier terminates and whether you can access it changes your entire design.
- Ask what the landlord allows. Core drilling, conduit, rooftop equipment and door hardware are all things a lease may restrict.
During design — before walls close
This is the window where everything is cheap. Once drywall is up, the same work costs multiples.
- Locate the IT room deliberately. Centrally if possible — copper runs cap at 100 meters including patch cords, and a closet in the corner of a large floor plate forces a second distribution frame. It needs power, cooling and enough space to work behind a rack.
- Specify the drop count per space, generously. Cable is cheap during construction. Two drops per desk, drops at every printer and display location, ceiling drops where access points will go, and drops at door locations for future access control.
- Get access-control door prep into the hardware schedule. Door prep ordered with the hardware costs almost nothing; retrofitting the same opening later means cored doors and surface raceway.
- Plan wireless from a survey, not a guess. AP locations need cable and often need to avoid the exact spots the architect wanted them.
- Decide phones early enough to affect cabling. Desk phones need drops.
Six to eight weeks before move-in
- Order the internet circuit. This is the long pole. Fiber installs routinely take 60 to 90 days and sometimes longer if construction is required. Businesses miss move-in dates over this more than anything else.
- Start number porting if you are keeping phone numbers. Porting has its own timeline and cannot be rushed at the end.
- Confirm equipment lead times. Switches, access points and door hardware all have supply variability.
Two to three weeks out
- Cabling installed, tested and certified — with results in hand.
- Rack built, switches configured, wireless tuned and verified with a walk test.
- Access control installed and every door’s fail state verified with the fire alarm interface.
- A temporary connection if the primary circuit is late, so day one is not dead.
The week of the move
Test everything with real users before they depend on it. Walk the wireless with a laptop and a phone. Call every extension. Badge every door. Print from every workstation. The problems you find on Thursday are inconveniences; the same problems on Monday are a crisis.
The mistake that costs the most
Treating IT as a move-in task rather than a design task. The low-voltage scope belongs in the drawings alongside electrical and mechanical. When it is added after construction, you pay for cored concrete, surface raceway and a second mobilization — for infrastructure that would have cost a fraction if it had been on the plan.
Building out or relocating? We do the whole scope as one project — office IT buildouts, structured cabling, wireless, phones and access control. Call (833) 306-3168 with the drawings.